Step 1
Customers should move any fragile lawn items into their garage as a precaution. There will be shingles and other debris being removed from the home and fragile items are at risk of being damaged if not moved prior to the roof replacement.
Step 2
Customers should notify their project manager of any fragile or sentimental lawn features that cannot be moved so that extra care can be taken to protect those areas during the roof replacement process.
Step 3
Customer vehicles will need to be moved into the garage if not being used or parked on the road away from the driveway entrance before the roof replacement begins so customers can come and go as needed to avoid driving over nails. A dump trailer/dumpster will likely be parked/placed in the driveway so it will be closer to the roof for easier removal of the old roofing system and overall clean-up during and after the roof replacement.